Design-Build WSA Upgrade Phase 2

Design and construct three earth-covered precast concrete munitions storage modules,  a one-half munitions storage module, a new CMU munitions maintenance and handling facility and a munitions holding pad.

  • Location: Undisclosed
  • Cost: $9,475,000
  • Owner: USACE
  • Designer: Tetra Tech / WJA
  • Construction Period: 11/2012 – 11/2014